PAVING OF YEREVAN’S STREETS 92% COMPLETED
Panorama.am
21:05 15/08/2007
The ongoing process of paving the streets of Yerevan is 92%
complete. As informed by the press service of city hall, the work
will be completely finished by September. To reach this deadline,
workers have a 3-tired graphic, as ordered by the mayor of Yerevan
at the most recent planning session.
We remind that this is in accordance with the planned conclusion date
of September 15, excepting the bridge at the corner of Tigran Mets
and Khanjian. That construction will last until October.
Starting tomorrow, work on the roads and bridges will begin, along
with work on the Baghramyan-Kievyan and Kievyan-Orbeli intersections
and on the "Artsakh" and "Freedom" boulevards. A list of expenses
has already been discussed and approved.
According to available information, cracks in the streets will also
be filled by the agreed-upon deadline. Additional workers will be
used to be able to complete the work on time.