Second High Voltage Power Transmission Line Laid b/w Armenia & Iran

SECOND HIGH VOLTAGE POWER TRANSMISSION LINE LAID BETWEEN ARMENIA AND IRAN
YEREVAN, NOVEMBER 29. ARMINFO. The second high voltage (220 KV) power
transmission line between Armenia and Iran is to be launched Nov 30
2004, says the director general of the High Voltage Power Transmission
Lines (HVPTL) company Sahak Abrahamyan.
The 82 km line was laid on Iran’s $8.4 mln credit. Its capacity is 200
MW. The line connects Shinuar and Agarak towns in Sunik and is
expected to redouble electricity flows between Iran and Armenia.
The general contractor is Sanir (Iran), the client HVPTL. The project
is based on the energy cooperation memorandum signed by Armenia and
Iran in July 2002. The Iranian credit is to be repaid in electricity
supplies. Dec 1 the sides are to sign a memorandum to lay the third
high voltage line.
Sanir is also the general contractor of the project to lay the
Armenian section of the Megri-Kajaran 42 km gas pipeline. The work is
to be started Nov 30 2004.
From: Emil Lazarian | Ararat NewsPress

Disclaimer: This article was contributed and translated into English by Emil Lazarian. While we strive for quality, the views and accuracy of the content remain the responsibility of the contributor. Please verify all facts independently before reposting or citing.

Direct link to this article: https://www.armenianclub.com/2004/11/30/second-high-voltage-power-transmission-line-laid-bw-armenia-iran/

Emil Lazarian

“I should like to see any power of the world destroy this race, this small tribe of unimportant people, whose wars have all been fought and lost, whose structures have crumbled, literature is unread, music is unheard, and prayers are no more answered. Go ahead, destroy Armenia . See if you can do it. Send them into the desert without bread or water. Burn their homes and churches. Then see if they will not laugh, sing and pray again. For when two of them meet anywhere in the world, see if they will not create a New Armenia.” - WS